The Earned Value Management (EVM) methodology is a project control technique that integrates scope, cost, and time, allowing managers to objectively assess the performance and progress of a project. EVM not only focuses on how much money has been spent or how much time has passed but also on the value that has been generated compared to the original plan. This approach makes it an essential tool for planning and controlling construction projects, where cost overruns and delays are common risks.
Basic Principles of the EVM Methodology
EVM is based on three fundamental principles:
1. Measurement of planned work (Planned Value): This involves establishing a baseline plan that defines what must be completed (scope), when it must be completed (schedule), and how much it should cost (budget). This planned value is known as Planned Value (PV), which reflects the value of work that should have been performed by a specific date.
2. Measurement of completed work (Earned Value): In this phase, the work that has actually been completed by the cutoff date is measured. Earned Value (EV) corresponds to the budgeted value of the work that has been completed, not just the cost incurred. This is essential in construction projects as it allows for an assessment of whether the actual progress is aligned with the plan.
3. Measurement of actual costs (Actual Costs): This metric consists of calculating the actual costs incurred to perform the work. It is known as Actual Costs (AC) and provides a direct comparison between what has been spent and what was planned for that work.
Key EVM Indicators
To effectively analyze the progress of a construction project using EVM, several key indicators are used. Below are the most important ones:
1. Schedule Performance Index (SPI): This indicator measures project performance relative to the schedule. It is calculated by dividing Earned Value (EV) by Planned Value (PV):
SPI = EV / PV
An SPI equal to 1 indicates that the project is progressing as planned. A value greater than 1 shows that the project is ahead of schedule, while a value less than 1 suggests a delay.
2. Cost Performance Index (CPI): The CPI measures the efficiency with which financial resources are being used in the project. It is calculated by dividing Earned Value (EV) by Actual Costs (AC):
CPI = EV / AC
A CPI of 1 means the project is on budget. A value greater than 1 indicates that the project is spending less than planned for the work performed, while a value less than 1 signals cost overruns.
3. Schedule Variance (SV): Schedule variance provides a monetary difference between the value of work that should have been completed and the value of work actually completed. It is calculated by subtracting Planned Value (PV) from Earned Value (EV):
SV = EV - PV
A positive SV value indicates that the project is ahead in terms of time, while a negative value suggests a delay.
4. Cost Variance (CV): Similarly, cost variance indicates whether the project is over or under budget. It is calculated by subtracting Actual Costs (AC) from Earned Value (EV):
CV = EV - AC
A positive CV means the project is saving costs, while a negative CV indicates overspending.
Application of EVM in Construction Projects
The EVM methodology is particularly useful in construction projects due to the inherent complexity and interrelationship between different activities. Below are some of its main applications:
1. Budget Control: EVM allows for the quick identification of project cost overruns. If the CPI shows a value below 1, managers can review areas where more resources are being spent than expected and take corrective measures, such as renegotiating contracts or reducing costs in other areas.
2. Schedule Management: By calculating the SPI, managers can detect if key activities are behind or ahead of schedule. This enables proactive planning, avoiding the ripple effect that delays can have on dependent activities.
3. Performance Forecasting: EVM is also useful for predicting future project performance through projections like the Estimate at Completion (EAC), which calculates the expected total project cost based on current performance:
EAC = BAC / CPI
Where BAC is the total budgeted cost of the project (Budget at Completion). Similarly, projections can be made for the schedule, estimating the project's completion date.
Keeping EVM Updated
To ensure the accuracy and usefulness of EVM, it is crucial to regularly update the EV, PV, and AC values. This is achieved through constant data collection from the field, monitoring of costs and physical progress, and periodic reviews of the schedule and budget. In construction projects, changes in scope, weather, and other external factors can significantly impact performance, so it is important for the EVM system to be flexible enough to adjust to these changes.
Conclusion
Earned Value Management is a powerful tool for planning and controlling construction projects. It offers a clear and quantifiable view of progress in terms of time and cost, enabling more informed and timely decision-making. Its ability to measure both the work performed and the associated costs provides a significant advantage over other control methods, which only focus on time or cost in isolation. To reap the maximum benefit from EVM, it is essential to implement the methodology from the beginning of the project and keep it updated throughout its execution.
In times of change, when agility and economy are needed at all levels, the use of specialized services provides that precise mix of capacity, effectiveness and efficiency that organizations need to succeed.
At DC&R we are able to meet these requirements with professional solvency and the experience of more than 30 years in complex engineering and construction environments for heavy industrial markets of high demand such as mining, gas & oil, or energy, as well as for infrastructure and commerce.
DC&R also offers technical assistance services to businesses that need to interact with engineering and construction companies, from tender and project management to contract administration.